Three winners of a competition for industrial communities have implemented energy solutions to become less dependent on unstable centralised energy supply.
In the Kharkiv region, a water supply system was upgraded to operate longer during power outages; in Drohobych, a solar power plant was installed and an educational and research space was established; and a social services center relocated from Selydove installed a solar thermal system at its residential care facility in Odesa region.
Each winning project received approximately UAH 500,000 (around EUR 10,000) in funding.
The competition was organised by NGOs Ecoaction and Alternatyva with the support of the UK Government as part of the project “Energy of the Future: New Opportunities for Industrial Communities.” It primarily targeted communities whose economies have traditionally depended on coal, gas, oil, or metallurgy.
“These projects demonstrate that a community’s energy resilience is built through practical solutions, such as ensuring access to water during power outages, enabling uninterrupted learning, or reducing social institutions’ dependence on fossil fuels. Importantly, communities are not only talking about these changes – they are already implementing them and seeing the first results,” said Tetiana Deriabkina, energy policy expert at NGO Ecoaction.
Seven Hours of Autonomous Water Supply in Kharkiv Region
In the settlement of Donets, part of the Slobozhanske community, the municipal utility company Komunalnyk upgraded the energy system supporting local water supply infrastructure. Reliable operation of the pumping equipment is especially important, as the system provides water to more than 1,800 residents, as well as a school, kindergarten, outpatient clinic, library, and other community facilities.
Three lithium batteries were added to the existing solar power system, increasing storage capacity by 60%. The equipment was also modernised, and an automated water-level control system was introduced.

As a result, the water supply system can now operate autonomously for around seven hours, while its operating time during power outages has increased by approximately 30%.
During May and June, electricity consumption from the grid decreased by about 70%. According to the projections, annual electricity savings will average around 30%.
For the community, this means not only lowering electricity costs but also a more reliable water supply during extended outages.
In Drohobych, a Solar Power Plant Became an Educational Lab
A hybrid rooftop solar power plant with a capacity of 13.53 kW and an energy storage system of approximately 20.4 kWh was installed at the Bohdan Lepkyi Scientific Lyceum of Drohobych.
The system covers part of the lyceum’s daytime electricity demand, charges batteries, and powers critical systems during grid outages.
The Drohobych Solar Lab project, implemented by the lyceum together with the relocated Donetsk National Technical University (DonNTU), went beyond simply installing a solar power plant. From the outset, the system was designed as an educational facility where students could explore energy generation, storage, and consumption in practice.

The project also secured significant co-financing. The Drohobych City Council contributed UAH 178,000 (around EUR 3,500), while DonNTU provided equipment worth UAH 250,000 (around EUR 5,000). In addition, Helvetyka Publishing House LLC plans to invest a further UAH 150,000–200,000 (EUR 3,000-4,000) in developing the educational space.
In May, the lyceum and DonNTU opened a joint Scientific and Advisory Space. Students have already begun researching renewable energy technologies and developing their own technical solutions.
As a result, the solar power plant has become not only a source of clean energy for the lyceum but also a foundation for hands-on learning and student research in renewable energy.
Solar Heat for a Relocated Social Services Center
Another project was implemented by the Municipal Institution “Center for Social Services Provision” of the Selydove City Council. Following the occupation of Selydove (Donetsk region), the institution relocated its operations to Mykolaivka (Odesa region), where the local residential care facility operates.
The facility provides round-the-clock care for 25 residents, including older people and persons with disabilities.
As part of the project, equipment for a solar thermal system was purchased and installed. The system is designed to use solar energy for water heating. Installation and external connection of the equipment were completed by the end of June. Once fully operational, the system is expected to reduce electricity consumption for hot water supply and lower the facility’s operating costs.

Selection Process
The winners were selected by a commission comprising representatives of Ecoaction, Alternatyva, and the British Embassy. Evaluation criteria included the relevance and feasibility of the project, its impact on community residents, innovation, and the efficiency of fund utilisation.